Alcatraz ferry dock: 2 of 5 pilings replaced, island closed Oct. 26 to Nov. 18

Every visitor to Alcatraz arrives by boat, and every boat ties up at one floating dock on the island. Since Monday, Oct. 26, that dock has been a work site: crews are driving new pilings to replace two of the five that hold it in place, and the National Park Service has closed the island to visitors until Nov. 18. It is the third time in 2026 that the dock has shut Alcatraz, and the last, if the plan holds. Here is what failed, why the job is squeezed into these weeks, and what you can still do on the water from San Francisco.

Closed to visitors (NPS)Oct. 26 – Nov. 18
Pilings being replaced2 of 5
Dock closures in 20263
Ferry trips a year to the island3,200+
Alcatraz Island seen across grey water from a ferry on San Francisco Bay, with a small boat passing in front and the Marin hills behind

What is wrong with the Alcatraz ferry dock

The landing on the island is a floating barge held in position by five vertical pilings driven into the bay floor. Two of them are being replaced.

Jan. 14, 2026
One piling fails. The island closes for nine days while Alcatraz City Cruises inspects all five: two need repair, three are sound. Ferries go back in service carrying fewer people per boat, with extra vessels to keep up with ticket sales.
April 2026
A six-day closure to strengthen the three good pilings. Afterwards the boats can run at greater capacity again, enough for the peak season.
Oct. 26 – Nov. 18, 2026
Third and final phase: pile driving and full replacement of the two remaining pilings. The island is closed to visitors throughout.
Nov. 30, 2026
The San Francisco Bay Conservation and Development Commission restricts in-water work after this date. The NPS says that limit is what sets the schedule.

Pile driving in the bay is regulated, and the window for it closes at the end of November, so the replacement could not wait for the quiet of winter. Once the two new pilings are in, the NPS expects the whole floating barge piling system to last 20 to 30 years.

The repair is not paid for with public money. Under its concession agreement, Alcatraz City Cruises, the park's ferry operator, covers the cost of inspecting and repairing the dock and is doing the work itself. The company runs more than 3,200 ferry trips a year and carries about 1.5 million visitors to the island.

Reopening: Nov. 19 at the earliestThe NPS says the repairs are expected to be finished by Nov. 18 and lists the closure as Oct. 26 to Nov. 18. Several outlets give Nov. 19 as the reopening day. That is the first possible day, not a date the park has confirmed, and both the NPS and Alcatraz City Cruises warn the timing depends on the weather and the progress of the work.

Ferries and cruises still running on the Bay

None of these lands on Alcatraz. They are the boats you can still take while the island is closed.

BoatFromWhat you getPrice
Bay Discovery Cruise (Alcatraz City Cruises)Pier 33, Alcatraz Landing90-minute round trip past Alcatraz, under the Golden Gate Bridge if weather allows, with an audio tour in 20 languagesFrom $44, fees and taxes included
Golden Gate Ferry to Angel IslandSan FranciscoFerry to Angel Island State Park, the bay's largest island; in winter it is the weekday public service to the island from the city$15.50 one way, $10 with Clipper or a contactless card, park entry included
Angel Island Tiburon FerryTiburonThe short crossing from Marin; on winter weekdays it runs as a charter onlySee the operator
Golden Gate Ferry tickets to Angel Island cannot be bought on the island, so buy the return with the outbound. They are non-refundable and valid for 90 days. Dogs are not allowed on the island; bikes ride free, first come, first served.

Alcatraz City Cruises' Bay Discovery Cruise page still shows its spring and summer timetable. We have not seen published November sailing times, so check availability before you plan around a departure.

Other West Coast ferries on this site

By The us.ferje.info newsroom — We keep the route pages for U.S. car and passenger ferries, from the San Juan Islands to the Outer Banks, and track the schedule changes, suspensions and dock work that decide whether you actually get across.

Built from the National Park Service's news release of Sept. 28, 2026, Alcatraz Island to Temporarily Close for Dock Repairs This Fall, and its questions and answers; the Alcatraz Island park page, checked on Oct. 27; Alcatraz City Cruises' Bay Discovery Cruise page; and Golden Gate Ferry's Angel Island fares. Photo: Nickey Ca, Wikimedia Commons, CC BY-SA 4.0, cropped to 16:9. The NPS says weather or other factors could move the dates; check the park page before you go.